dimarts, 9 de juliol del 2019

Stonehenge £2bn road tunnel project funding uncertain, MPs warn

Ministers claim the scheme will improve the world heritage site by taking traffic away from it.
A £2bn project to open a road tunnel beneath the Stonehenge world heritage site in 2026 is being put at risk by uncertainty over how it will be financed, MPs have warned.
Ministers have claimed the scheme is affordable, deliverable and will improve Stonehenge by taking the sight and sound of lorries and cars away from the ancient monument and reducing traffic congestion.
But the public accounts committee (PAC), which scrutinises government spending, said the project was at the mercy of the forthcoming spending review, the timing of which is uncertain because of Brexit.
The committee flagged up concerns expressed by a senior Department for Transport (DfT) official, who told members when evidence was taken by the committee: “If we want this scheme to continue, and to continue in a sensible and efficient way to the current timeframe, we cannot wait another year, or however long it takes to carry out a spending review.”
The MPs’ report coincides with heated public hearings arranged as part of a six-month examination by a panel of five inspectors. In May, the National Audit Office said risks and uncertainty surrounded the plan for the two-mile tunnel.

Fast moving traffic flashes past Stonehenge on the A303 in Wiltshire, on the day a 5.5 billion package of transport improvements for England, including a 183 million road tunnel to protect Stonehenge was announced by the Government. * Containing around 3 billion of road improvements, the package included the go-ahead for a 1 billion widening to four lanes of one of the busiest stretches of road in the UK - the M6 between Birmingham and Manchester. 17/02/04: A public inquiry into the controversial re-routing of roads around the iconic ancient monument opens today. Under the proposal traffic would pass through a 1.3 mile tunnel, but some environmental organisations feel that it should be longer.
The PAC’s conclusions are another blow to the project. The committee said: “Decisions on how to fund the project are on the critical path for the planned opening date of 2026 and are now at the mercy of the much-awaited spending review. Delaying those decisions further will jeopardise the opening date.
“If uncertainty about funding is not resolved before 2020, the timetable and viability of [the] Stonehenge tunnel project will be put at risk.”
The tunnel project was to be financed under the PF2 private finance initiative, but in October 2018, the chancellor, Philip Hammond, cancelled future private finance deals, including for Stonehenge.
The DfT said it and the Treasury remained committed to the project, with the latter releasing funding of £21.5m during 2019–20 to keep the scheme going. Transport chiefs do not expect to fund the project from the 2020-2025 road investment strategy, instead making the case for additional funding as part of the next spending review.
Fast moving traffic flashes past Stonehenge on the A303 in Wiltshire, on the day a 5.5 billion package of transport improvements for England, including a 183 million road tunnel to protect Stonehenge was announced by the Government. * Containing around 3 billion of road improvements, the package included the go-ahead for a 1 billion widening to four lanes of one of the busiest stretches of road in the UK - the M6 between Birmingham and Manchester
According to the PAC, Highways England must have funding certainty by the end of the year if it is to begin the commercial process of finding a construction contractor in time to keep to its 2026 target opening date.
“The timetable looks very challenging. We understand that between now and 2021, when construction is scheduled to start, as well as getting clarity over funding, Highways England must also obtain the necessary planning consents, negotiate with contractors to find a preferred supplier and complete the detailed design for the project,” the committee said.
In this Sunday, June 21, 2015 file photo, the sun rises as thousands of revellers gather at the ancient stone circle Stonehenge to celebrate the Summer Solstice, the longest day of the year, near Salisbury, England. British authorities have approved a contentious road tunnel under Stonehenge _ but have altered its route so it doesn't impede views of the sun during the winter solstice, it was reported on Tuesday, Sept. 12, 2017
There is also concern from the committee as to whether the project will be delivered within budget. “Given the department’s performance on other major projects in recent years, for example Crossrail, where costs have overrun to the tune of nearly £3bn, we are more cautious,” the MPs said.
Possible hitches cited by the PAC include finding new sites of archaeological interest during construction.
A DfT spokesperson said: “This government is committed to investing in the south-west and the A303 [including the tunnel] and A358 schemes [a linked project further west] are on track to be delivered to their respective timetables. Development work is continuing as planned.”

L'atac nord-americà de Doolittle contra el Japó va canviar el corrent de la Segona Guerra Mundial

Fa 80 anys: el Doolittle Raid va marcar el dia que sabíem que podríem guanyar la Segona Guerra Mundial. Com a patriòtic nord-americà, durant...